JFK Millennium Partners (JMP) was selected by the Port Authority of New York and New Jersey to develop Terminal 6 at JFK International Airport. Our team is comprised of Vantage Airport Group, American Triple I (ATI), RXR Realty, and JetBlue. Together with our design-build partner, Aecom Hunt, we are excited to build and manage a state-of-the-art new international terminal that will anchor the north side of the airport and help transform JFK into a modern, 21st century airport.

Terminal 6 by the Numbers

$4.9 Billion
                redevelopment

$4.9 Billion redevelopment

with more than $2.7bn in planning, design, and construction services

1.2 million square feet

1.2 million square feet

terminal complex, new critical supporting roadways, utilities, aircraft apron, and ground transportation center

10 aircraft
                gates

10 aircraft
gates

First five gates to open by 2026; with terminal completion by 2028

30% MWBE/LBE Participation Goal

Exceeding 30% MWBE/LBE Participation goal

4,000+
                jobs created

4,000+
jobs to be Created

100,000 square feet

100,000 square feet

of exceptional passenger amenities

JMP has selected AECOM Hunt as its design-build partner for delivery of the new Terminal 6. Delivered in two parts, this project will offer significant contract and employment opportunities

Our Design-Build Team

JMP has selected AECOM Hunt as its design-build partner for delivery of the new Terminal 6. Delivered in two parts, this project will offer significant contract and employment opportunities.

We are committed to meeting or exceeding the Port Authority’s goal of 30% utilization of minority and women-owned business enterprises (MWBEs), including 20% for minority-owned businesses (MBEs), 10% for women-owned business enterprises (WBEs), 10% for local business enterprises (LBEs), and 3% for service-disabled veteran-owned businesses (SDVOBs). Competitive bids from local businesses representing the Borough of Queens and surrounding areas will be prioritized.

Our MWLBE/SDVOB Participation Goals

We are committed to meeting or exceeding the Port Authority’s goal of 30% utilization of minority and women-owned business enterprises (MWBEs), including 20% for minority-owned businesses (MBEs), 10% for women-owned business enterprises (WBEs), 10% for local business enterprises (LBEs), and 3% for service-disabled veteran-owned businesses (SDVOBs). Competitive bids from local businesses representing the Borough of Queens and surrounding areas will be prioritized.

JMP has selected AECOM Hunt as its design-build partner for delivery of the new Terminal 6. Delivered in two parts, this project will offer significant contract opportunities.

Our Design-Build Team

JMP has selected AECOM Hunt as its design-build partner for delivery of the new Terminal 6. Delivered in two parts, this project will offer significant contract and employment opportunities

We are committed to meeting or exceeding the Port Authority’s goal of 30% utilization of minority and women-owned business enterprises (MWBEs), including 20% for minority-owned businesses (MBEs), 10% for women-owned business enterprises (WBEs), 10% for local business enterprises (LBEs), and 3% for service-disabled veteran-owned businesses (SDVOBs). Competitive bids from local businesses representing the Borough of Queens and surrounding areas will be prioritized.

Our MWLBE/SDVOB Participation Goals

We are committed to meeting or exceeding the Port Authority’s goal of 30% utilization of minority and women-owned business enterprises (MWBEs), including 20% for minority-owned businesses (MBEs), 10% for women-owned business enterprises (WBEs), 10% for local business enterprises (LBEs), and 3% for service-disabled veteran-owned businesses (SDVOBs). Competitive bids from local businesses representing the Borough of Queens and surrounding areas will be prioritized.

Terminal 6 Construction Timeline

Construction

Construction

2023-2028

Operations

Operations

From 2025 onwards

Terminal 6 Construction Timeline

Construction

Construction

2023-2028

Operations

Operations

From 2025 onwards

Upcoming Bid Opportunities

BP # Project Description Bid Issue Date Estimated Bid Submission Date
04B Masonry -– Interior Fitout 10/20/2023 12/24/2023
05C Ornamental Metals & Railings 10/10/2023 12/14/2023
05D Metal Fabrications – Interior Fitout 10/10/2023 12/14/2023
06A Architectural Woodwork / Panels 12/22/2023 2/28/2024
06B Architectural Woodwork / Casework 12/8/2023 2/28/2024
07C Interior Caulking 3/7/2024 5/8/2024
08B Overhead Doors 3/7/2024 5/8/2024
08C Interior Glass and Glazing 12/22/2023 2/28/2024
09B Drywall and Ceilings 12/22/2023 2/28/2024
09C Tile 3/7/2024 5/8/2024
09D Terrazzo 3/7/2024 5/8/2024
09F VCT, Base, Carpet, Wood Flooring 3/7/2024 5/8/2024
09G Painting and Wallcovering 5/16/2024 6/22/2024
09H Intumescent Painting 10/10/2023 12/14/2023
09X Misc. Finishes 9/19/2023 12/8/2023
10A Toilet Partitions and Accessories 5/7/2024 12/8/2023
10B Terminal Signage 5/16/2024 7/22/2024
10X Other Specialties 7/24/2024 10/1/2024
11A Loading Dock Equipment 5/16/2024 7/22/2024
11B Food Service Equipment 7/24/2024 10/1/2024
11X Misc. Equipment 7/30/2024 10/1/2024
12A Hold Room Furniture 5/16/2024 7/22/2024
12X Misc. Furnishings 7/20/2024 10/1/2024
13X Special Construction 7/30/2024 10/1/2024

Already Certified?

If you are already certified or are in the process of obtaining certification, please ensure that your business profile in the relevant MWBE/SDVOB directory is current and accurate. This includes updating your commodity codes, work categories, and contact information. We will send out requests for interest to potential bidders based on the specific work categories that each company is certified to undertake.

How to Get Certified

Interested in working with us?
View our open contracting opportunities.

view all

Access Construction Bid Opportunities

Register in Building
Connected.

Login | building connected

Complete a
pre-qualification
application.

Note that AECOM is involved in Terminal 1 with Tishman Construction and at Terminal 6 with Hunt Construction at JFK Airport.

There is a separate prequalification application per development team. If you are interested in being considered for both projects, do not start the applications simultaneously. Complete one application first to facilitate the seamless transition of information from one to the next. Please be reminded that you need to complete both applications if you want to register for both T1 and T6 work. Data transfer will reduce your data input, but you need to register under both project websites if you want to bid on both.

Access Concessions Opportunities

Concession Opportunities

Concession Opportunities

Receive updates about
concession opportunities.

View Opportunities
Categories II/III Concessions

Categories II/III Concessions

[email protected]

Close Form

Join our mailing list here to receive email updates on upcoming bid opportunities.

Join

Browse the online public calendar for upcoming community events related to the JFK redevelopment.

View Events

Contact Us

General Supplier Diversity Inquiries

[email protected],Click Here Brianna Allen

Category I – Financial & Professional Services

[email protected],Click Here Jean Kristensen

Categories II/III & Construction

[email protected],Click Here Mei-Ling Rodriguez

Categories II/III Concessions

[email protected]Click Here